Why procurement plans fail before the first tender

By Victor Manan Nyambala, , 6 minute read

When a purchase goes wrong, the post mortem usually focuses on the tender. The evaluation took too long. The supplier failed to deliver. The paperwork did not satisfy the auditor. These are real problems, but they are rarely the root cause. In most organisations the failure was set in motion weeks or months earlier, when nobody planned the purchase properly.

Procurement is the point where a programme’s intentions meet the market. If the intentions are vague, late or unrealistic, the market will not fix them. Here are the five planning failures we see most often in NGOs, public bodies and growing businesses, and what to do about each one.

1. The procurement plan is written after the budget, not with it

Budgets are often built by programme and finance teams who estimate unit costs from last year’s figures or a quick online search. By the time procurement sees the budget, the quantities, prices and timelines are fixed and frequently wrong.

The fix is simple to describe and harder to practise. Bring procurement into budget preparation. A procurement officer can tell you within a day whether a price is realistic, whether the item is available locally and how long a compliant process will take. That conversation costs almost nothing. Discovering the problem after the grant is signed costs a great deal.

2. Specifications describe a brand, not a need

“Twenty laptops, the same as last time” is not a specification. Neither is a product code copied from a supplier’s catalogue. Specifications written around a brand limit competition, invite challenge and often fail donor rules that require fair, open tendering.

A good specification describes what the item must do, the conditions it must work in and the standards it must meet. It is written by the person who needs the item, reviewed by procurement and agreed before the tender is issued. Where the requester does not have the technical knowledge, procurement should help them get it, not write the specification for them.

3. Every purchase is treated as a one off

Organisations that buy the same things repeatedly, such as fuel, stationery, vehicle maintenance, hygiene items or hotel services, often run a separate process each time. Each process takes weeks. Each one carries the same risks. Each one earns a slightly different price.

Framework agreements change this. You run one competitive process, select one or more suppliers and agree prices and terms for a fixed period. After that, individual orders can be placed in days. The organisation saves time, the supplier has the certainty to invest in better service and the auditor sees one clean process instead of twenty rushed ones.

4. Lead times are guessed, not measured

Ask most programme teams how long a medium value tender takes and you will hear “about a month”. Measure it and the real figure, from approved request to goods received, is often two or three times that.

You cannot plan around a number you have never measured. Start recording a small set of dates for every purchase: request approved, tender issued, award, order placed, goods received. Within a quarter you will know your actual cycle times by category and value band. Feed those figures back into planning and the plan starts to match reality.

5. Nobody owns the whole plan

In many organisations each project keeps its own list of purchases. Procurement sees them one at a time, as requests arrive. Nobody has the full picture, so nobody can spot that three projects are about to buy the same item from three different suppliers in the same month.

A consolidated procurement plan, reviewed monthly by programme, finance and procurement together, solves this. It does not need sophisticated software. A well structured spreadsheet, owned by one person and updated on a fixed day, is enough for most organisations to start with.

Where to begin

If you recognise more than two of these failures, do not try to fix all five at once. Start by measuring your real lead times for three months. The data will tell you where the biggest delays sit, and it will give you the evidence you need to change how budgets and plans are built.

Good procurement is not about running faster tenders. It is about arriving at the tender with a clear need, a realistic timeline and a market that is ready to respond.